This project default manages the setting of the item shipment promised contract date on the Change Order (CO) approval.
-
Module(s) affected by this setting: Agreement > Agreements Overview > Agreement Details (> Approval Sequence), Open Procurement Interface.
-
List of Values: New (N) and Old (O, default).
-
If set to O, the promised contract date of the previous supplement is kept (this applies only to item shipments having a release note quantity).
-
If set to N, the promised contract date is not overwritten on CO approval, the CO value is kept (this applies only to item shipments having a release note quantity).
-