ZP_SP_POLI - Intergraph Smart Materials - 10.2 - Help - Hexagon

Intergraph Smart Materials Web Help (10.2)

Language
English
Product
Intergraph Smart Materials
Subproduct
Web
Search by Category
Help
Smart Materials/Smart Reference Data Version
10.2

This project default controls the split tag functionality in Expediting, Traffic, and Site.

  • Once you have created an agreement of either type PO or NOC, you cannot change the setting of this project default any longer.

  • This project default cannot be set on the discipline level.

  • Module(s) affected by this setting: Expediting, Traffic, and Site.

  • List of Values: Y and N (default).

  • If set to Y, the detail tags are always created on the agreement line item level, even if the first split occurs in a subsequent module of Agreement (Expediting, Traffic or Site).

  • If set to N, the detail splits are placed on the item shipment level if they are created by Expediting, Traffic, or Site. Only if the first splits were already created in Procurement (on Quote Details or Agreement Line Items), further splits are also created on the agreement line item level, too, if later in Expediting, Traffic or Site need additional splits are needed.