All objects that exist in the project but don't exist in the Plant must be claimed.
-
All objects that exist in the Plant but don't exist in the project (that is, they were deleted) must have been claimed.
-
All objects that exist in both the Plant and the project must be identical if not claimed.
-
The claim state must be valid for the project.
-
If any claim on an object on this drawing is invalid then check in cannot occur.
-
The timestamp on all objects that exist in the project must be earlier than or equal to the timestamp on the drawing.
-
Last Publish Date > Drawing date.
-
Check In not allowed if Drawing is in a Re-create state.
-
The Verify for Checkin for new drawings should ensure that all items on the drawing have been claimed.