Using Projects in an Existing Workshare Collaboration - Intergraph Smart P&ID - 11 - Help - Intergraph

Intergraph Smart P&ID Help

Language
English
Product
Intergraph Smart P&ID
Search by Category
Help
Smart P&ID Version
11
Smart Engineering Manager Version
12
SmartSketch Version
11

You must discontinue all Workshare collaboration in a plant before you can create projects in the plant. In other words, if the plant structure contains active Satellites, the Enable Projects command remains unavailable. We recommend completing the following tasks before enabling the plant for projects.

  1. Transfer all drawings to the host.

  2. Delete all satellites.

  3. Disable the plant for Workshare.

  4. Enable the plant for projects.

  5. Create a project to serve as the host.

  6. Enable the project for Workshare.

  7. Create satellite slots in the project host.

  8. Create satellites.

  9. Check out or fetch drawings at the host, then re-distribute drawings back out to the satellites.