Before performing this scenario, ensure that you have completed all the prerequisite activities described in Sample Project Workflows.

  1. In Project 1, check out Drawing B from the Plant.

  2. Open Drawing B.

  3. Fence select all items and claim the selected items.

  4. Exit Drawing B.

  5. In Project 2, fetch Drawing B from the Plant.

  6. Open Drawing B.

  7. Fence select all items except both OPCs and claim the selected items.

    The claim status for the items indicates that they have already been claimed by another project.

  8. Change the Tag Sequence Number for the vessel to 110.

  9. Change the Construction Status of the vessel from New to Existing.

  10. Exit Drawing B.

    Drawing B becomes Drawing B'.

  11. In Project 1, open Drawing B.

  12. Place an Area Break around the vessel and Nozzle N1.

  13. Place an Alt Dgn Press-Temp Equipment Label on the Area Break.

  14. Select the Area Break, right-click, and on the shortcut menu, select Select Contents.

  15. In the Properties window, if you cannot see the pressure and temperature properties, select Show Case Data for the Select Set to display those properties.

  16. Assign Alt Dgn Max Press of 100 psi.

  17. Assign Alt Dgn Max Temp of 101 F.

  18. Exit Drawing B.

    Drawing B becomes Drawing B''.

  19. In Project 1, check in Drawing B'' with removal of the drawing from the project.

  20. Select Project > Project Status.

  21. Select Complete Project.

  22. Select Merge Project to merge Project 1 into the Plant.

    If you complete and merge Project 1, you will not be able to use it for the other workflows unless you delete and re-create Project 1. If you want to continue without deleting and re-creating the project, you should skip both the Complete and Merge operations until you have completed all of the workflows.

  23. In Project 2, check out Drawing B'' without replacing the existing P&ID.

    Drawing B'' becomes Drawing B' in Project 2.

  24. In Project 2, attempt to check in Drawing B'.

    Invalid Claim prevents check-in.

  25. In Project 2, open Drawing B' and compare it with the drawing in the Plant.

  26. Do the following:

    1. Refresh Drawing B' for the Area Break and label and all other differences that result in invalid claims (see Compare and Refresh Drawing Versions).

    2. Place a Revision Cloud around the Control Valve (FV-...) and the Actuator (ACT-...).

    3. Place a Revision Triangle on the Revision Cloud. Label the Revision Triangle RT- 1.

    4. Exit Drawing B'.

    Drawing B' becomes Drawing B'''.

  27. Check in Drawing B'''.

    PPM All Outputs Graphic

Key



Check out drawing

Fetch drawing

Continuity between procedure steps (an arrow indicates changes to the drawing or to drawing item data)

Check in drawing

Check-in unsuccessful