Each day on the horizontal axis can have two separate columns. The right column can consist of several different portions that all have a different color. The height of the right column generally changes when the charts are updated. This column can exceed the capacity line.

The left column contains works that are assigned to the work group and workplace according to their static scheduling.

The software calculates the length of the columns according to time calculation rules saved in the system. The vertical axis has automatic scaling, so workloads with different durations are always visible in the charts.

However, it is possible to limit the automatic scaling by selecting Limited Scaling on the toolbar.