Work Group Dependent Values list consists of the workload times based on Work Groups. The list contains workload times of tasks, which are dependent on the work group as well as the weight and/or length of the part or plate/remnant.

The drop-down list Work Group contains work groups saved by the System Settings application.

The group with tasks performed based on weight and/or length of a part is selected first. The lower and upper limit for the weight and/or length are entered in the edit fields. These weights and lengths can be the size of the plate/remnant to be cut or the cut part.

After the name of the task existing in the window there is:

  • the note (W) when it is dependent on the weight.

  • the note (L) when it is dependent on the length.

  • the note (W, L) when it is dependent on both the weight and length.

The part-specific time value is entered in the following fields:

Part Picking Time.

Bending Part Lifting Time.

Bending Part Turning 1 Time.

Bending Part Turning 2 Time.

The following are the fields in which the entered time values are quotation/order item-specific. The program divides the values by the amount of the parts in the item so the part-specific workload time is achieved.

Grinding Setup Time.

Bending Setup Time.

The following are the fields in which the entered time values are quotation/order-specific. The program divides the values by the amount of the parts with the same material code in the quotation/order so the part-specific workload time is achieved.

Plate Lifting Time.

Scrap Lifting Time.