Follow the steps below to create a project,
-
Click Administration > Project Configuration.
-
Select Create New Project.
-
Click Add Item to add a new row.
The CREATE PROJECT screen appears.
-
Enter the following information in Project Details tab
-
Project Name
-
Description
-
Project Number
-
Project Job No
-
Contract
-
Client Name
-
Project Location
After providing the project details, you have an option to enable Revision Management and Lot Management for your project.
-
Enable Revision Management for a Project
WQMS provides an option to select or apply Revision Management business logic for a project during project creating. These settings are applicable only for WQMS Fabrication site.
-
After you enter the project details, click the Revision Management tab.
Workflow for Revision Management
The following swimlane explains how to setup a project, configure the project settings, and how to apply revision management for a project.
-
Select the following options:
-
Is Revision Management Required? - Select Yes if you require Revision Management for your project. Select No, if you do not require Revision Management for your project.
Do not use Delete with Status Update, Delete and Add item in Piping welds when revision management is enabled for a project.
-
Data Source - Select the data source for your project. Data source represents from which tools (such as 3D, Spoolgen) the weld and wed component data is loaded into WQMS.
-
Revision Scheme - Revision scheme defines the format of the revision such as revision type, number of characters allowed, status (valid or invalid). You can only select one format for a project.
WQMS supports the following formats as shown in the table below: 1-9,1-9, 1,1, 11, 10
-
Revision Type |
Major |
Minor |
Major No of Characters |
Minor No of Characters |
Valid |
Invalid |
---|---|---|---|---|---|---|
Rev01A-99Z |
01-99 |
A-Z |
2 |
1 |
01A |
1A |
Rev1A-9Z |
1-9 |
A-Z |
1 |
1 |
1A |
10A |
Rev11-99 |
1-9 |
1-9 |
1 |
1 |
11 |
10 |
A01-Z99 |
A-Z |
01-99 |
1 |
2 |
A99 |
A100 |
A1-Z9 |
A-Z |
1-9 |
1 |
1 |
A9 |
A10 |
RevAA-YY |
A-Y |
A-Y |
1 |
1 |
AY |
AZ |
Once you set the values Is Revision Management Required, Data Source, and Revision Scheme for a project, you cannot modify them later. You can modify Weld Revision Properties, Weld Component Revision Properties for a project anytime.
After selecting the above options, you must select the weld revision properties and weld components revision properties for which you want to apply Revision Management business logic.
-
Weld Revision Properties - Click the Weld Revision Properties tab, select the required weld properties from the list and click the right arrow to move the property to Selected Weld Properties list .
-
Weld Component Revision Properties - Click the Weld Component Revision Properties tab, select the required weld component properties from the list and click the right arrow to move the property to Selected Weld Components Properties list .
You can assign and deassign the properties using the right and left arrows.
The selected weld revision properties and weld component revision properties will be used while comparing the properties of welds in old revision and new revision. If there are modifications in the selected properties, then Revision Management business logic will be applied.
Enable Lot Management for a Project
WQMS provides an option to enable Lot Management for a project during project creating. These settings are applicable only for WQMS Fabrication site.
-
After you enter the project details, click the Lot Management tab and select Is Lot Management Required option as Yes.
-
Click Save. After you save, you can manage lots using Lot Management module.
For default projects (project number), Lot management and Revision management is enabled automatically.
Once the welding is completed, the welds are sent to Visual Inspection stage. In Visual Inspection, a Report of Inspection (ROI) is created for the welds. Once you accept the welds, Lots are created automatically based on the criteria defined in NDE matrix module.
To accept the welds,
-
Navigate to Piping > Visual Inspection
-
Select Report of Inspection.
-
Select the ROI and click Manage Inspection Items to view welds under that ROI.
-
Select the weld under Manage Inspection Items section and click Accept
-
Enter the Inspection Name, select the Inspection Date and Accept Reason.
-
Click Save. The lot are created automatically.
-
-
The Lot management module is displayed even though it is set as No for a project.
-
If Lot management is set to true for a project, you must disable Apply NDE in Piping module, and NDE Definition module.
-
If lot management is enabled for a project, you must make "IS BSR NDT Required" column items read only in Visual Manage Inspection Items column set.