When you create an internal or external work area definition for one or more selected
object types, a scheduler task is created automatically. Run asynchronously, this
task relates the filter to the 3D objects shared for that work area definition. A
notification in your inbox will keep you apprised of the status of the scheduler task
and indicate whether the task was completed successfully.
What properties are included in this notification?
The following properties are included and tracked in the notification for this scheduler
task.
-
SDXWorkAreaRelateItemsProgressStatus - The progress status of the relationships of
items to the work area.
-
SDXWorkAreaRelatedItemsInProjectCount - The number of items in the project related
to the work area.
-
SDXWorkAreaTotalItemsInProjectCount - The total number of items to relate in the project.
-
SDXWorkAreaRelatedItemsInAsBuiltCount - The number of items related in the as-built
configuration.
-
SDXWorkAreaTotalItemsInAsBuiltCount - The total number of items to relate in the as-built
configuration.
-
SDXWorkAreaRelateItemsFailureMessage - The message that appears when relating items
to the work area fails.
When you create an internal work area definition without selecting any object types,
you must manually synchronize the work area definition with the 3D objects by doing
these steps:
-
Click Integration > 3D Work Area Definitions.
-
On the Actions menu of the applicable work area definition, click Apply Filter to Work Area.