Allows you to add or delete official cut-off dates for a project. The cut-off dates defined here are the dates when the program will automatically run a roll up and recalculate the progress data.
Official cut-off dates are those scheduled here and run automatically. Unofficial cut-off dates are those created when you run a manual rollup.
Cut-off Dates - Displays a list of the official cut-off dates already defined for the project.
Delete - Removes the selected date from the list.
Add - Adds the date selected on the calendar to the list of cut-off dates.
Roll-ups and reporting occur on the dates you specify here.