Allows you to add an event definition to a production step or substep. Examples of events that can be associated with steps include sign-off of specific deliverables revisions and the issue of deliverables on a transmittal for specified reason.
This dialog box appears when you click the Events button at the bottom of the Add Step dialog box when working with design workpacks and workpack templates.
Event - Choose an event that must meet a specified condition before the step is completed.
Condition - Choose the condition that must be met by the event before the step is completed.
Percentage progress for step - Indicate what portion of the step is represented by this event. In other words, if the step is 50% complete once the selected step meets the selected condition, enter 50 in this field.
Add - Places the event you are creating into the table.
Remove - Deletes any event selected in the table.