Update Step Duration and Dates dialog box - SmartPlant Foundation - IM Update 48 - Help - Hexagon

SmartPlant Foundation Help

Language
English
Product
SmartPlant Foundation
Search by Category
Help
SmartPlant Foundation / SDx Version
10
SmartPlant Markup Plus Version
10.0 (2019)
Smart Review Version
2020 (15.0)

Allows you to make changes to the duration and target and planned dates for a workflow step.

Enter new duration - Type the number of days the step should now take to complete. Changing the duration updates the target dates for this and future steps. The planned date remains the same. If there are parallel steps, changes to the duration are based on the longest duration.

Target date - Displays the target date for the step. Changing the planned date must be done manually; it is independent of the other dates. Changing the target date on this dialog box updates only that property of the step; the duration of this step and dates for other steps are not updated.

Planned date - Displays the planned date for the step. This value can be edited manually, but will not be updated as a result of other changes in the dialog box.