The Accept Replan command replaces the plan and construction dates with those provided for replan and replan construction. This command is available from the Replan submenu on the Progress menu.

When a replan is accepted, the following changes are made to the workpack details:

  • The Plan Start and Plan End dates for the workpack are replaced with the Replan Start and Replan End dates.

  • The Construction Start and Construction End dates are replaced with the Replan Construction Start and Replan Construction End dates.

  • The Replan Start, Replan End, Replan Construction Start, and Replan Construction End date fields on the Plan Details tab of the Design Workpack Create/Update Form dialog box are cleared.

For each deliverable in the workpack, the following changes are made:

  • The plan dates for each step are replaced with the replan dates.

  • The forecast dates and replan dates for each step are cleared.

  • The Actual dates for each step are not affected.

  • If a deliverables new plan dates do not correspond to an available timestring, a new timestring will be created and related to it by the Accept Replan process. The new timestring will also be available on the appropriate workpack. It is named with a prefix of "RP" and an incremental number.

See Also

Accept the replan