Register a deliverable with a workpack - SmartPlant Foundation - IM Update 48 - Help - Hexagon

SmartPlant Foundation Help

Language
English
Product
SmartPlant Foundation
Search by Category
Help
SmartPlant Foundation / SDx Version
10
SmartPlant Markup Plus Version
10.0 (2019)
Smart Review Version
2020 (15.0)
  1. Find the deliverable that you want to associate with a workpack.

  2. Right-click on the deliverable, and click Register for Progress.

  3. In the Progress section of the Details tab, view the weighting for the deliverable.

    The Register for Progress dialog box differs slightly for Design and Activity deliverables.

  4. In the Man hours section, indicate the number of man hours that have been budgeted for the completion of this deliverable and the number of man hours that will be required to complete it. These figures are maintained based on the allocated man hours for the workpack and the weighting and level of completion of the deliverable.

  5. On the Steps tab, review the Options selected for the deliverable. If you want to enable the downstream forecasting or calculation override features for this deliverable, make sure the appropriate check box is selected.

    SHARED Tip These check boxes are available only if those features have been selected as available for the workpack when it was created.

See Also

Register for Progress command
SPF DTC ADMIN Register for Progress Dialog Box DLG