The following is an example of an activity workpack.

Example of activity workpack progress

The following diagram shows an example of activity workpack progress. Four items (in this case vendor documents) have been registered for activity progress (for example, a review process). These are the deliverables (or activity items).

Initially, the documents have no status code (first step is document received). When the documents are first returned by the supplier, documents 1 and 2 have progressed to step 2 and have status code 1, documents 3 and 4 have progressed to step 3 and have status code 2. Total progress is 50%.

Document 2 then progresses to step 3 and documents 3 and 4 progress to step 4 and are now complete. Document 1 reverts to step 1 and now has no status code. (Activity progress is dynamic and the progress items can move back as well as forward.) Total progress is now 70%.

In the final stage, documents 1 and 2 both progress to step 4, status code 3. Total progress is now 100%.