Activity progress accrual

For activity deliverables, progress is calculated based on the return statuses of activity items.

The first time an activity deliverable gets an actual receipt date, the first step completes (even if it was one deliverable out of 100). The completion of this step then sets the benchmark for the rest of the forecast dates. All the other steps gain levels of progress based on how many deliverables out of the total deliverables on the activity have been returned at that step's status code.