Add progress cut-off dates - SmartPlant Foundation - IM Update 48 - Help - Hexagon

SmartPlant Foundation Help

Language
English
Product
SmartPlant Foundation
Search by Category
Help
SmartPlant Foundation / SDx Version
10
SmartPlant Markup Plus Version
10.0 (2019)
Smart Review Version
2020 (15.0)
  1. Click Progress > Edit Progress Cut-Off Dates in the Desktop Client.

  2. In the calendar displayed on the Edit Project Cut-off Dates dialog box, select a date you want to establish as an official cut-off date.

  3. Click Add to place that date in the list of official cut-off dates defined for the project.

Roll-ups and reporting occur on the dates you specify here.

See Also

Edit Progress Cut-Off Dates command
SPF DTC ADMIN Edit Project Cut-Off Dates Dialog Box DLG