Change the replan dates - SmartPlant Foundation - IM Update 48 - Help - Hexagon

SmartPlant Foundation Help

Language
English
Product
SmartPlant Foundation
Search by Category
Help
SmartPlant Foundation / SDx Version
10
SmartPlant Markup Plus Version
10.0 (2019)
Smart Review Version
2020 (15.0)

To change the replan dates for a deliverable:

  1. While in replan mode, right-click the deliverable in the Desktop Client, and click Update Progress in the shortcut menu.

  2. Select the replan dates.

  • The default replan dates are based upon the actual dates provided for steps. If an actual date does not exist for a step, the replan date will be based on the forecast date of the step. If a step has no forecast date, the replan date is based on the plan date.

  • These dates must fall within their Replan Start and End dates for the workpack.

  • The replan dates do not have to obey the time string that is set for the current deliverable. When the replan is accepted, the system will create a new time string if necessary.