Dates entered during replan mode are only applied when a replan is accepted.
-
While in replan mode, click Progress > Replan > Accept Replan in the Desktop Client.
-
Click OK to accept the replan.
When a replan is accepted, the following changes are made to the workpack details:
-
The Plan Start and Plan End dates for the workpack are replaced with the Replan Start and Replan End dates.
-
The Construction Start and Construction End dates are replaced with the Replan Construction Start and Replan Construction End dates.
-
The Replan Start, Replan End, Replan Construction Start, and Replan Construction End date boxes on the Plan Details tab of the Design Workpack Create/Update dialog box are cleared.
For each deliverable in the workpack, the following changes are made:
-
The plan dates for each step are replaced with the replan dates.
-
The forecast dates and replan dates for each step are cleared.
-
The Actual dates for each step are not affected.
-
If a deliverable's new plan dates do not correspond to an available time string, a new time string will be created and related to it by the Accept Replan process. The new timestring will also be available on the appropriate workpack. It is named with a prefix of "RP" and an incremental number.