This option provides one revision scheme for the plants and a different one for the projects.
-
Create two revision schemes, one for each level. For example:
-
RevA for Config level = 1.
-
RevA1 for Config level = 2.
-
There is no need to set Take next major revision on merge property on RevA, because the system automatically sets the property merging from project to plant and forces a change in revision scheme. However, setting the property makes the intentions clearer.