This procedure allows you to change the status of a project submitted for stage gate review back to In Development.
-
Navigate to Admin > Portfolios Admin > Workflow Admin.
-
Click the Actions list and select Re-Open Submitted Stage Gate Project.
-
The Re – Open Submitted Stage Gate Project dialog box appears.
-
Select Project ellipsis to select the required project
-
(Optional) Type a Comment.
-
Click the Run button. The Re-Open Submitted Stage Gate Project confirmation box appears.
-
Click the OK button.