This process will transfer the Project Schedule Resource Assignment requests for the selected Project to Staging Utilization for review and approval by the Resource Manager.
-
Click the Actions list and select Push Resource Assignments to Resource Request Portal.
-
Click the Project ellipsis and select the project from which you want to transfer resources to Staging Utilization.
-
Click RUN and then OK.
Only the resource assignments that have Hours will be pushed for approval.