This procedure allows you to view the graph plotted between cost and hours of the resource assigned to an activity.
The Resources Assigned must be time-phased before seeing them on this chart.
-
In the Activity Scheduler panel, select the activity row for which you want to view the resource allocation graph.
-
In the Activity Task Scheduler Tabs panel, click the Resource Allocation Graph tab to view the graph.