To view the Project Performance Summary Units report, perform any of the following actions.
-
View the report in the Earned Value screen:
-
Navigate to Progress > Earned Value.
-
Click the Reports tab.
-
Click the Project Performance Units hyperlink. A dialog box appears with a title Project Performance Summary (Hours).
-
Click the Project ellipsis to select the required project. By default, the last selected project appears.
-
Click the Project Period ellipsis to select the required period. By default, the last selected period appears.
-
Click the Run button. The preview of the report appears.
-
-
View the report from the Reports menu:
-
Navigate to Reports > Earned Value > Project Performance Units.
-
Click the Project ellipses to select the required project. By default, the last selected project appears.
-
Click the Project Period ellipsis to select the required period. By default, the last selected period appears.
-
Click the Run button. The preview of the report appears.
-