Actual start and end dates may be updated manually or imported. This data is used in reports, and is also utilized when calculating earned value for project objects with a progress method of Fixed Formula 0/100 or Fixed Formula 0/50/100. The user must manually ensure that the start date for a given project object falls before the end date.