Details
-
To get to the Re-issued state, the permitted work must have been Suspended and re-issued when work could proceed again.
-
The Performing Authority and Issuing Authority verify that all the controls and isolations are in place for the work to proceed.
Actions
-
Select Accept - All the controls and isolations are in place for the work to proceed.
-
User permissions: Performing Authority or Issuing Authority
-
For hot work permits, ensure that the gas tests are up to date.
-
The Accept window appears. Confirm that the controls and isolations are in place, sign, and select Confirm.
-
State change: Re-issued > Live
-
-
Select Suspend - If the work can't proceed due to environmental issues or the performing team aren't available to continue the work.
-
User permissions: Issuing Authority
-
The Suspend window appears. Enter a reason for the suspension, sign, and select Confirm.
-
State change: Re-issued > Suspended
-
Time trigger
-
If the Issued Until date is past while the permit is in the Re-issued state.
-
State change: Re-issued > Suspended
-