j5 Control of Work Help

Language
English
Product
j5
Search by Category
Help
j5 Version
30

Issued - De-isolation For Testing

Details

  • To get to the Issued DFT state, the permitted work must have been Suspended DFT and then issued for testing when the de-isolation was complete.

  • The Performing Authority and Issuing Authority verify that the area has been safely de-isolated for the testing to proceed.

Actions

  • Select Accept DFT - The area has been safely de-isolated for the testing to proceed.

    • User permissions: Performing Authority or Issuing Authority

    • For hot work permits, ensure that the gas tests are up to date.

    • The Accept DFT window appears. Confirm the conditions are suitable for testing, sign, and select Confirm.

    • State change: Issued DFT > Live DFT

  • Select Suspend DFT - The area needs to be further prepared for testing (for example, more safety precautions need to be put in place)

    • User permissions: Issuing Authority

    • The Suspend DFT window appears. Enter a reason for the suspension, sign, and select Confirm.

    • State change: Issued DFT > Suspended DFT

Time trigger

  • If the Issued Until date is past while the permit is in the Issued DFT state.

    • State change: Issued DFT > Suspended DFT