Click Start > All Programs > Intergraph Batch Services > Intergraph Batch Manager.
-
Select the computer name in the tree view.
-
Select the batch queue.
-
Select Queue > Properties to display the Queue Properties Dialog.
-
On the General tab, make sure Disable Job Inflow while Running Job is not selected.
-
Click Scheduling.
-
Set the Run Limit, which defines the number of jobs that can run simultaneously. The allowable range is 1-60. The default setting is 1.