Temporarily freeze a schedule to compare the actual work done against the work that you scheduled. Frozen activity schedules cannot be updated.
To freeze and unfreeze activity schedules:
-
Select Work > WO Planning > WO Scheduling.
-
Right-click on the form, and then choose Freeze/Unfreeze.
-
Specify this information:
Freeze/Unfreeze - Select Freeze to freeze the schedule, or select Unfreeze to unfreeze the schedule.
From Date/To Date - Specify the starting and ending dates for the freeze period.
Department - Specify the department for which to freeze or unfreeze schedules.
-
Click Submit.