Specify and view accomplishments on an existing work order activity that occurred on a specific date. Accomplishment records provide a way to document activities that were completed in the field. Multiple accomplishment records may exist for a specific work order activity or for a specific work date.

  1. Select Work > Work Order.

  2. Select the work order for which to enter accomplishments and then click the Accomplishments tab.

  3. Specify this information:

    Activity - Specify an activity.

    Type - Specify a user code for the accomplishment type.

    Date Worked - Specify the date worked for the specified accomplishment

  4. Optionally, specify the System Level, Assembly Level, Component Level, Action Code, Quantity, Unit of Measurement, Crew, and Employee.

  5. Select the desired activity.

  6. Click Submit.